Our colocation provider is moving some systems to a new cabinet, with
enhanced power delivery and cooling. colobus will be moved to the new
rack on Thursday, August 21 between 23:00 and 23:59. I will be
combining this with a needed kernel upgrade, which will occur at
approximately 22:30. Most likely the move will be completed at the
earlier end of the range. I will be performing the kernel upgrade,
rebooting to test, and then re-racking the system.
Additionally we will be provisioned for serial console access at the
time (this is not service affecting).
Maintenance Window: 22:30 - 23:59.
Service impact: System will be rebooted for kernel upgrade, back up
briefly, and then down during the rack move.
If you have any questions/concerns, please call me at 603-325-5306, or
email. My apologies in advance for any inconvenience.
Cheers,
Dan
--